Rodas Hotel
Download Case StudyChallenge:
In the hospitality industry, managing energy costs poses significant challenges, impacting overall efficiency and profitability. Prior to our solution implementation, the hotel faced escalating energy expenses and operational inefficiencies. Post-COVID financial uncertainties led to hesitancy in upfront investments, prompting us to offer an Opex model. Our retrofit-friendly solution seamlessly integrated with existing operations, minimizing disruptions while focusing on energy-saving measures.
Solution:
Installation and Execution
Installing and commissioning HVAC systems at a hotel near Mumbai International Airport posed unique challenges due to the continuous influx of travellers and consistently high occupancy rates. The 75F and TPTCL team identified opportunities for energy savings, meticulously planning shutdowns during non-peak hours to minimize disruption. They coordinated closely with the client and engaged in meetings with the chiller OEM to optimize the impact of the solution. A significant challenge was installing during non-peak hours. Fortunately, 75F’s out-of-the-box IoT-based BMS suite, renowned for its rapid implementation, retrofit-friendly design, and ability to optimize HVAC operations in existing buildings, proved invaluable. The installation team strategically timed their work to align with AHU shutdowns required by operational protocols. During these brief windows, the 75F and TPTCL team efficiently deployed all necessary solutions. Moreover, the team conducted a thorough energy audit and detailed energy accounting to ensure optimal performance and maximize energy savings. This comprehensive approach underscored the team's commitment to enhancing efficiency and reducing operational costs.
Results:
Energy Savings
Energy Savings installation began in August 2023 and concluded by October 2023, requiring only 90 days for installation and commissioning. Energy data started flowing from December 2023 onwards. A significant improvement was the incorporation of remote monitoring solutions, providing real-time data access for efficient control and enhanced occupant comfort. Additionally, these capabilities played a crucial role in optimizing energy usage, leading to notable savings. Within three months, the 75F solution saved 17,400 kWh of energy on the chiller plant and AHUs, representing a 16% reduction compared to the baseline benchmark. Through our collective efforts, we've successfully reduced CO2 emissions by a remarkable 13,746 tons, a feat akin to planting 203.58 trees.
Collaborative Success
In the successful execution of our hospitality energy optimization project, invaluable support was provided by key stakeholders from Hiranandani Hotel and Tata Power. Mr. B. L. Walunj, Mr. Kundan Attarde, and Mr. Simon from Hiranandani Hotel exhibited unwavering commitment and collaboration throughout the project, ensuring its smooth implementation and success. Additionally, Mr. Amit Jain, Mr. Arpan Chhaya, and Ms. Ritika Jain from Tata Power played instrumental roles, bringing expertise and dedication to the table, thereby contributing significantly to the project's achievements. This collaborative effort exemplifies the power of partnership and collective action in driving sustainable solutions and achieving mutual success in the hospitality industry.